The Response to Submissions for the Environmental Impact Statement (EIS) of the Bendemeer Solar Farm has been submitted and is currently under assessment. You can view the status of the project below: Major Projects Portal
Following public submissions and ongoing community engagement, considerable amendments have been made to the proposed solar project. These amendments can be accessed below, along with a summary of the studies undertaken in the EIS, which can be accessed below:
Project Amendment Summary EIS Summary
The Bendemeer Renewable Energy Hub solar project will create a range of social and economic opportunities for the Bendemeer region and local surrounding areas, as well as creating environmental benefits for the New England region to build a sustainable future with renewable energy.
The proposed solar farm will generate an estimated 577,000 MWh of renewable energy, and reduce greenhouse gas emissions by 420,000 tonnes CO2, per year. For scale, the project will generate enough energy equivalent to powering 74,000 NSW homes!
The solar farm will cover an area of up to 350.8 hectares, and there will be approximately 430,000 solar modules created for the project. The solar panel technology will be monocrystalline silicon, and will use up to 5,000 single-axis mounting technology trackers. With a project nameplate (DC) rating of 255 MW, the total disturbance footprint will span across approximately 389 hectares (961 acres).


The Bendemeer Renewable Energy Hub team have created a space for Frequently Asked Questions about the solar project asked by the community to be answered all in one place. The FAQ page can also be found in the Solar Fact Book, that has been developed for the solar project to give community members and residents a greater understanding of the project. These books will be updated as the projects progress.
An online copy of the most up to date information book can be found here – Solar Information Book

The timeline below indicates where the solar project is up to in the State Significant Development Application process, and will be updated as necessary as the project progresses.
You can also access information regarding the project on the NSW Government’s Major Projects Planning Portal.
Comprehensive analysis of wind and solar resources, environmental and engineering constraints, and proximity to electricity grid, services and infrastructure.
Site identification for the solar and wind farm, and execution of landholder agreements.
Commencement – 2019
Execution of Land Option Agreements – December 2020
All State Significant developments are required to prepare a comprehensive Environmental Impact Statement to ensure the project achieves an appropriate balance between environmental, social and economic considerations and is in the public interest.
Scoping Report submitted – January 2022
SEARS Received – March 2022
EIS Submission – July 2023
Public Exhibition – August 2023
Response to submissions – September 2023 – April 2025
DPHI Assessment – May – November 2025
Recommendation – anticipated early 2026